Northwick Park Hospital

Project details

Construction of new hospital spine road and S278 improvements on Watford Road.

Client / Contractor

VolkerFitzpatrick Ltd

Programme

84 weeks

Location

Northwick Park Hospital, Harrow, London

July 22 – Feb 24 (live)

Period
Subcontract

NEC Option A lump sum

Scope of Works
  • Site clearance
  • Deep drainage 5m deep 1200mm & 1400mm concrete pipes (500m)
  • In-situ flow control chambers, manholes & catch pits up to 5m deep
  • Gully pots and leads
  • Bulk earthworks and road construction (13000m3)
  • Ducting works (3300m)
  • Granite and conservation kerbs (2000m)
  • Edgings (2000m)
  • Section 278 works