Ash Road Bridge

Project details

New bridge over the North Downs Railway Line near the village of Ash in Surrey, together with associated approach roads, traffic calming, new junctions with existing roads and alterations to existing roads to tie the new roads into the existing infrastructure.  

Client / Contractor

VolkerFitzpatrick Ltd

Programme

62 weeks

Location

Ash, Aldershot

Sept 23 – Dec 24 (live)

Period
Subcontract

NEC Option A lump sum

Scope of Works
  • Embankment fill earthworks (70000m3)
  • Cut / fill to flood areas and ponds (10000m3)
  • 6N backfill to abutments / wingwalls and back of wall drainage, culverts & structures (20000m3)
  • Road box cut, capping and type 1
  • Carrier drainage, gullies and leads (2800m)
  • 70m 4.5m x 2.4m PCC box culverts
  • Section 278 Works
  • Ducting & Utility Trenching (2500m)
  • Kerbs, Edgings and timber edging (4900m)
  • Topsoiling (11000m3)
  • Maintenance tracks
  • Site clearance